Back

Licence for Electricity Generation in Cogeneration (CHP)

How to handle the procedure

You can complete the procedure:
  • by visiting the office in person
  • by sending documents by post

What you should know and who can apply

Licence for electricity generation in cogeneration

If you intend to conduct business activity in the field of electricity generation in cogeneration, you must obtain a licence.

Cogeneration is the simultaneous production of heat and electricity (or mechanical energy) within the same technological process.

Licensing applies to electricity generation in cogeneration units, regardless of the installed capacity or the amount of energy produced.

You do not need a licence if you intend to generate electricity:

  • in sources with a total installed electrical capacity not exceeding 50 MW, which are not classified as renewable energy installations or cogeneration units;
  • in a micro-installation — a renewable energy installation with a total installed electrical capacity not exceeding 50 kW, connected to a power grid with a rated voltage below 110 kV, or with a thermal capacity in cogeneration not exceeding 150 kW, where the total installed electrical capacity does not exceed 50 kW;
  • in a small installation — a renewable energy installation with a total installed electrical capacity greater than 50 kW and less than 500 kW, connected to a power grid with a rated voltage below 110 kV, or with a thermal capacity in cogeneration greater than 150 kW and not exceeding 900 kW, where the total installed electrical capacity is greater than 50 kW and less than 500 kW;
  • from agricultural biogas;
  • exclusively from agricultural biogas in cogeneration;
  • exclusively from bio-liquids, as defined in the Act of 20 February 2015 on Renewable Energy Sources.

Conditions for obtaining a licence

You may be granted a licence if:

  • you have a registered office or place of residence in an EU Member State, Switzerland, Turkey, or an EFTA Member State that is a party to the EEA Agreement (Norway, Iceland, Liechtenstein);
  • you have financial resources ensuring proper performance of the activity, or you can document the ability to obtain such resources;
  • you have the technical capabilities to ensure proper performance of the activity;
  • you will employ personnel with appropriate professional qualifications for operating networks, equipment, and installations;
  • you hold a decision on land development and zoning conditions;
  • you are not in arrears with taxes constituting state budget revenue, or you have obtained an exemption, deferral, instalment plan, or full suspension of enforcement of the relevant tax authority’s decision.

When to apply

Koncesję uzyskaj przed rozpoczęciem wykonywania działalności gospodarczej w zakresie wytwarzania energii elektrycznej w kogeneracji.

Where to apply

Submit your application to the relevant regional office of the Energy Regulatory Office (URE).
Choose the office responsible for the area where your company is registered or where you reside.

Submit your application to the URE headquarters in Warsaw if it concerns a renewable energy installation that uses the following fuels in the electricity generation process:

  • biomass or biomass with other fuels
  • bio-liquids with other fuels
  • biogas with other fuels
  • agricultural biogas with other fuels

Regional offices of the Energy Regulatory Office (URE) in Poland:

  • Northern Regional Office – Gdańsk (Pomorskie and Warmińsko-Mazurskie Voivodeships)
  • Southern Regional Office – Katowice (Śląskie and Świętokrzyskie Voivodeships)
  • South-Eastern Regional Office – Kraków (Małopolskie and Podkarpackie Voivodeships)
  • Eastern Regional Office – Lublin (Lubelskie and Podlaskie Voivodeships)
  • Central-Western Regional Office – Łódź (Mazowieckie and Łódzkie Voivodeships)
  • Western Regional Office – Poznań (Wielkopolskie and Kujawsko-Pomorskie Voivodeships)
  • North-Western Regional Office – Szczecin (Zachodniopomorskie and Lubuskie Voivodeships)
  • South-Western Regional Office – Wrocław (Dolnośląskie and Opolskie Voivodeships)

Energy Regulatory Office (URE)
ul. Towarowa 25a, 00-869 Warsaw

Step-by-step instructions

1. Prepare and submit your licence application

Required documents

1. Application for a licence to generate electricity in cogeneration (CHP)

Download:

The document may be submitted as:

  • Original

Additional information

The application for a licence to conduct business activity in the field of electricity generation should include:

  1. Identification of the applicant, including its registered office, branch office in the territory of the Republic of Poland or place of residence, along with their addresses, and the names of the attorneys authorized to perform legal actions on behalf of the entrepreneur;
  2. Specification of the subject and scope of the activity for which the licence is to be issued;
  3. Information on the applicant’s previous business activity, including financial statements from the last 3 years, if the entity conducts business activity;
  4. Specification of the period for which the licence is to be granted, including the start date of the activity;
  5. Specification of the resources available to the entity applying for the licence to ensure proper performance of the activity covered by the application;
  6. The number in the register of entrepreneurs in the National Court Register (KRS), if the entrepreneur has such a number, or the number in an equivalent register of a Member State of the European Union, the Swiss Confederation, a Member State of the European Free Trade Association (EFTA) – party to the Agreement on the European Economic Area, or Turkey, as well as the tax identification number (NIP).
2. Excerpt from the register of entrepreneurs of the National Court Register (KRS)
The document may be submitted as:
  • Copy
  • Original
  • Certified copy
3. Certificate confirming the assignment of a Tax Identification Number (NIP)
The document may be submitted as:
  • Copy
  • Original
  • Certified copy
4. List of persons authorized to represent the applicant

The document may be submitted as:

  • Original
5. List of persons authorized to represent the applicant and members of the supervisory board

The document may be submitted as:

  • Original
6. Certificates of clean criminal record

The document may be submitted as:

  • Original
7. Company agreement or articles of association

The document may be submitted as:

  • Copy
  • Certified copy
8. List of entities with significant influence over the enterprise or exercising control or joint control

The document may be submitted as:

  • Original
9. Statement by the entrepreneur confirming that no bankruptcy petition has been filed and that the entity is not in liquidation

The document may be submitted as:

  • Original
10. Statement by the entrepreneur confirming that it has not been removed from the register of regulated activities in the last three years

The document may be submitted as:

  • Original
11. Confirmation of VAT registration

The document may be submitted as:

  • Original
  • Certified copy
Additional information
The confirmation template is specified in Annex No. 2 to the Regulation of the Minister of Development and Finance of 27 December 2016 on the templates of documents related to the registration of taxpayers for value-added tax purposes.
12. Certificate of excise number assignment

The document may be submitted as:

  • Copy
  • Original
13. Statement confirming no charges have been brought for criminal or fiscal offences against the entrepreneur, supervisory board members, or persons authorized to represent the enterprise
The document may be submitted as:
  • Original

Additional information

The statement concerns the filing of charges in a case involving the commission of a criminal or fiscal offence.

14. Statement confirming that all personnel operating the network, installations, and equipment used in the licensed activity hold valid qualification certificates
The document may be submitted as:
  • Original
Additional information
Employees should hold qualification certificates issued under the provisions of the Energy Law Act, as well as qualification certificates issued under other regulations, authorizing them to operate the relevant networks, installations, and equipment.
15. Power of attorney for administrative matters
Download:
The document may be submitted as:
  • Original
  • Certified copy
16. Proof of payment of stamp duty for the power of attorney
The document may be submitted as:
  • For inspection
  • Copy
  • Original
  • Certified copy
17. Proof of payment of stamp duty
The document may be submitted as:
  • For inspection
  • Copy
  • Original
  • Certified copy
18. Document confirming legal title to facilities and installations
The document may be submitted as:
  • Copy
  • Original
  • Certified copy
Additional information
For example: notarial deed, excerpt from the land and mortgage register, extract from the land register, lease agreements, lending agreements, leasing agreements, purchase invoices, etc.
19. Description of technical parameters and condition of equipment used for electricity generation
The document may be submitted as:
  • Copy
  • Original
  • Certified copy
20. Diagram of the cogeneration unit’s equipment, indicating the boundary of the energy balance
The document may be submitted as:
  • Copy
  • Original
  • Certified copy
21. Zoning decision or decision on the location of a public purpose investment
The document may be submitted as:
  • Copy
  • Certified copy
Additional information
The zoning decision specifies:
– the type of investment;
– the conditions and detailed rules for land development and construction resulting from separate regulations, in particular regarding:
  • conditions and requirements for the protection and shaping of spatial order,
  • environmental protection, human health, cultural heritage and monuments, as well as contemporary cultural assets,
  • infrastructure and transport services,
  • requirements concerning the protection of third-party interests,
  • protection of buildings in mining areas;
– the boundaries of the investment area, marked on a map at an appropriate scale (i.e. 1:500 or 1:1000; for linear investments, a scale of 1:2000 is acceptable).
22. Decision on the location of a public purpose investment
The document may be submitted as:
  • Copy,
  • Certified copy,

Additional information

The decision on the determination of the location of a public purpose investment specifies:
  • the type of investment;
  • the conditions and detailed rules for land development and construction, as derived from separate regulations, particularly regarding:
    • conditions and requirements for the protection and shaping of spatial order,
    • environmental protection, human health, cultural heritage, historical monuments, and contemporary cultural assets,
    • infrastructure and transport services,
    • requirements for the protection of third-party interests,
    • protection of buildings located in mining areas;
  • boundary lines of the investment area, marked on a map at an appropriate scale (i.e., 1:500 or 1:1000; for linear investments, a scale of 1:2000 is acceptable).
23. Building permit

The document may be submitted as:

  • Original
24. Occupancy permit
The document may be submitted as:
  • Copy,
  • Certified copy,
25. Occupancy permit or notice of completion of construction with a statement confirming no objection from the competent building supervision authority
Download:
The document may be submitted as:
  • Copy
  • Certified Copy
26. Statement confirming no objection from the competent building supervision authority
The document may be submitted as:
  • Original,
  • Certified copy,
27. Information on compliance with the local spatial development plan
The document may be submitted as:
  • Original,
  • Certified copy,
28. Decision and protocol from the Office of Technical Inspection (UDT)
The document may be submitted as:
  • Copy,
  • Certified copy,
29. Integrated permit
The document may be submitted as:
  • Copy
  • Certified Copy
  1. The integrated permit should meet the requirements specified for the following permits:
  • for the release of gases or dust into the air
  • water permit for the discharge of wastewater into water or into the ground
  • for waste generation
as well as the water permit for water abstraction.
Therefore, the permit should specify:
  1. the type and parameters of the installation relevant from the perspective of pollution prevention;
  2. the permissible emission levels under normal operating conditions of the installation, not exceeding those resulting from proper operation, for each operational variant;
  3. the maximum allowable duration of technologically justified operating conditions deviating from normal, particularly during start-up and shutdown of the installation, as well as the conditions or parameters characterizing the installation’s operation that define the end of start-up and the beginning of shutdown, and the conditions for releasing substances or energy into the environment in such cases;
  4. if it affects the determination of environmental protection requirements:
  5. a) the required date for ending the operation of the installation,
  6. b) the permissible total duration of continued operation and the method of documenting this time;
  7. sources of generation or locations of release of substances or energy into the environment;
  8. the date from which emissions are permitted, in the case of a new installation;
  9. identification of the main operator of the installation or the scope of responsibility of individual operators for designated parts of the installation, in accordance with Article 183b;

 

  1. The integrated permit shall specify – for installations requiring such a permit – the scope and method of monitoring emission levels in accordance with the monitoring requirements set out in BAT conclusions, if available. In the absence of BAT conclusions, BAT reference documents may be considered, insofar as they exceed the requirements referred to in Article 147 of the Environmental Protection Law and those specified in the Regulation of the Minister of the Environment of 30 October 2014 on requirements for conducting emission measurements and measurements of water abstraction.
  2. The integrated permit may specify – for installations requiring such a permit – the scope and method of monitoring emission levels beyond the requirements set out in BAT conclusions, if justified by specific environmental protection considerations.
  3. The integrated permit should also specify, for installations requiring such a permit:
    1. the type of activity conducted;
    2. methods for achieving a high level of environmental protection as a whole;
    3. requirements ensuring the protection of soil, land, and groundwater, including measures to prevent emissions into these media and methods for systematic supervision, if necessary;
    4. for installations requiring an initial report – the method for conducting systematic risk assessment of contamination of soil, land, and groundwater with hazardous substances that may be present on the site due to the operation of the installation, or the method and frequency of testing for contamination and measuring the concentration of such substances in groundwater, including sampling;
    5. methods for limiting transboundary environmental impacts;
    6. noise emission levels determined by permissible noise indicators outside the facility, expressed as LAeq D and LAeq N, in relation to land designated for residential use, hospitals and care homes, buildings for permanent or temporary stay of children and youth, and areas designated for health resorts, recreation, and mixed residential-service use; including the daily operating schedule of noise sources and anticipated variants;
    7. quantity, condition, and composition of wastewater, if not discharged into water or into the ground;
    8. quantity of water used, unless the conditions referred to in Article 202(6) apply (i.e., this quantity is not specified if the water is used solely for the installation requiring an integrated permit);
    9. methods for preventing and mitigating the effects of failures and the requirement to report failures, unless this concerns facilities with increased or high risk of failure (as referred to in Article 248(1));
    10. procedures for decommissioning the installation, including methods for removing negative environmental impacts resulting from its operation, if such impacts are anticipated;
    11. methods for ensuring efficient energy use;
    12. scope, method, and deadline for submitting annual information to the authority issuing the permit and to the voivodeship environmental inspector, enabling assessment of compliance with the permit conditions, in areas not covered by Article 149 of the Environmental Protection Law.
  4. The integrated permit may specify additional requirements for the installation if necessary to achieve a high level of environmental protection as a whole. Furthermore, the permit shall define the method and frequency of testing for contamination of soil and land with hazardous substances and measuring the concentration of such substances in groundwater.
  5. The justification of the integrated permit should include an assessment of the costs of achieving emission limit values (based on which a derogation from these limits may be granted).
30. Waste generation permit
The document may be submitted as:
  • Copy
  • Certified Copy

Additional Information

The permit for waste generation specifies (in accordance with Article 188(2), (2a), (2b), and (3) of the Environmental Protection Law of 27 April 2001):

  1. The type and parameters of the installation relevant from the perspective of pollution prevention;
  2. If it affects the determination of environmental protection requirements:
    1. The required date for ending the operation of the installation,
    2. The permissible total duration of continued operation and the method of documenting this time;
  3. Sources of generation or locations of release of substances or energy into the environment;
  4. The date from which emissions are permitted, in the case specified in Article 191a;
  5. Identification of the main operator of the installation or the scope of responsibility of individual operators for designated parts of the installation, in accordance with Article 183b.

The permit for waste generation additionally specifies:

  1. The tax identification number (NIP) and REGON number of the waste holder, if assigned;
  2. A list of types of waste intended for generation, including their basic chemical composition and properties;
  3. The quantity of each type of waste intended for generation per year;
  4. Methods for preventing waste generation or reducing the quantity of waste and its negative environmental impact;
  5. A description of the method of further waste management, including collection, transport, recovery, and disposal;
  6. The location, method, and type of stored waste;
  7. Fire safety conditions resulting from the fire safety report.

The permit may specify, if justified by specific environmental protection considerations:

  1. Procedures for decommissioning the installation;
  2. The amount and form of financial security for claims;
  3. Required actions, including a list of technical measures aimed at preventing or reducing emissions, and if such actions are to be implemented during the permit period – also the deadline for their implementation;
  4. The type and quantity of energy, materials, raw materials, and fuels used, taking into account the requirements referred to in Article 143(1–5);
  5. The scope and method of monitoring technological processes, including the measurement and recording of emission levels, insofar as they exceed the requirements referred to in Articles 147 and 148(1);
  6. Procedures in case of damage to measuring equipment used for monitoring technological processes, if its use is required;
  7. The method and frequency of submitting the information and data referred to in point 5 to the authority issuing the permit and to the voivodeship environmental inspector.
31. Document confirming the installed electric capacity of the cogeneration unit
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
32. Technical connection conditions to the power grid (so-called grid connection conditions)
The document may be submitted as:
  • Copy
  • Certified Copy
33. Connection agreement
The document may be submitted as:
  • Copy
  • Certified Copy
34. Technical inspection protocol, approval and commissioning of energy equipment issued by the power system operator to whose grid the cogeneration unit is connected
The document may be submitted as:
  • Copy
  • Certified Copy
35. Protocol verifying the correct operation of metering and settlement systems (so-called OTS commissioning protocol)
The document may be submitted as:
  • Copy
  • Certified Copy
36. Power output diagram
The document may be submitted as:
  • Original
  • Certified Copy
37. Characteristics of the type of biomass/biogas planned for use in the cogeneration unit
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
38. Fuel feeding system diagram
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
39. Sample (preliminary) purchase agreement for the type of biomass used in the unit
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
40. Results of operational and movement tests
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
41. Manufacturer’s opinion on the capability of the generation equipment to burn biomass exclusively
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
42. Information on the fuel used for electricity generation
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
43. Information on the use or non-use of auxiliary fuel in the renewable energy source
The document may be submitted as:
  • Original
44. Document confirming that technical safeguards prevent electricity generation from auxiliary fuel
The document may be submitted as:
  • Original
45. Authentication documentation: installation for production and procedures for settlement of energy from renewable sources
The document may be submitted as:
  • Original
46. Opinion on the prepared authentication documentation
The document may be submitted as:
  • Original
47. Summary of projected annual revenues and costs for the licensed activity, for a minimum of 3 years
The document may be submitted as:
  • Original
48. Financial statements from the last 3 years
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
49. Documents confirming possession or ability to obtain financial resources sufficient for proper performance of the licensed activity
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy

Additional Information

Bank guarantees, insurance guarantees, and guarantee agreements.
50. Certificate of no tax arrears or statement of tax arrears (ZAS-W)
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
Additional Information
The certificate includes, among others:
  • Applicant’s identification details
  • Address of the registered office or place of residence
  • Information on the absence or existence of tax arrears (including their title, period, and amount)
  • Information on interest for late payment or its absence, along with the amount
  • Information on deferral or installment payment of tax liabilities
Upon the applicant’s request, the certificate may also include information:
  1. Whether the applicant is subject to:
    a) Proceedings aimed at identifying tax arrears and determining their amount
    b) Enforcement proceedings in public administration, including those related to non-tax liabilities of the applicant
  2. Concerning:
    a) Periods from which the arrears originate and their titles
    b) Taxes for which payment deadlines have been deferred or for which payment has been divided into installments
51. Certificate of no arrears in social security contributions (ZUS)
The document may be submitted as:
  • Copy
  • Original
  • Certified Copy
Additional Information
The certificate includes:
  1. Number
  2. Applicant’s details (name/company name, address, NIP, REGON, PESEL, ID card/passport series and number)
  3. Confirmation that the applicant has no arrears in the payment of contributions to:
  • Social insurance
  • Health insurance
  • Labour Fund, Guaranteed Employee Benefits Fund
  • Bridging Pensions Fund
  1. The date as of which the applicant has no arrears
52. Bank certificate on the status of funds, turnover, loans, and enforcement titles against the entrepreneur
The document may be submitted as:
  • Copy
  • Original

 

Documents confirming compliance with formal-legal and organizational requirements
  1. An excerpt from the register of entrepreneurs – National Court Register (KRS) – obtained no earlier than 3 months before submission to the licensing authority (if registration in the KRS is required);
  2. A certificate of assignment of a tax identification number (NIP) – if NIP information is missing from other submitted documents;
  3. If the applicant is a legal entity (e.g. joint-stock company or limited liability company), an organizational unit without legal personality (e.g. general partnership), or a foreign entrepreneur operating in Poland through a branch, submit:
  • A list of persons authorized to represent the applicant
  • A list of supervisory board members
  • A certificate from the National Criminal Register confirming no criminal record of all persons authorized to represent the entrepreneur
  • A certificate from the National Criminal Register confirming no criminal record of all supervisory board members
If the entrepreneur, shareholder, or management board member is not a Polish citizen, submit an appropriate certificate issued by the competent authority of the country of citizenship of the person concerned. Also attach a sworn translation of the certificate into Polish.
  1. If the application is submitted by a natural person who is an entrepreneur, submit a certificate confirming no criminal record;
  2. The company’s articles of association or statute, if the applicant is a company;
  3. A list of all entities that have a significant influence on your company or exercise control or joint control over it, as defined in Article 3(1)(34), (35), and (36)(a), (b), (e), and (f) of the Accounting Act. Attach a certificate from the National Criminal Register confirming no criminal record of these entities. In the case of an entity registered abroad or not being a Polish citizen, also submit appropriate information issued by the competent authority of the country of registration or citizenship of the entity concerned, along with a sworn translation into Polish;
  4. A statement by the entrepreneur that no bankruptcy petition has been filed against them and that they are not in liquidation (in the case of civil law partnerships, each partner must submit a statement);
  5. A statement by the entrepreneur that they have not been removed from the register of regulated activities in the last 3 years due to a decision prohibiting the applicant from conducting the registered activity because of:
  • Submission of a false statement regarding compliance with legal requirements for conducting the activity
  • Failure to correct violations of legal requirements for conducting the activity within the deadline set by the authority
  • Gross violation of legal requirements for conducting the activity
In the case of civil law partnerships, each partner must submit a statement;
  1. Confirmation of registration of the applicant as a VAT taxpayer (e.g. certificate);
  2. Submit a certificate of assignment of an excise number, if applicable;
  3. A statement by the entrepreneur (and persons authorized to represent them, as well as supervisory board members) confirming that there are no grounds for suspending the proceedings due to the issuance of an order to present charges against the applicant or the aforementioned persons in connection with a criminal or fiscal offense related to the conducted activity. In the case of civil law partnerships, each partner must submit a statement;
  4. A statement by the entrepreneur that all persons employed in the operation of networks, installations, and equipment used for licensed activities hold qualification certificates required under the Energy Law and other relevant regulations authorizing them to operate such networks, installations, and equipment;
  5. Power of attorney – if you are represented by an attorney – along with proof of payment of the applicable stamp duty for granting the power of attorney;
  6. Proof of payment of the stamp duty for issuing the license.

 

Documents confirming that technical conditions required for proper performance of business activity are met
  1. Documents confirming the entrepreneur’s legal title to facilities and installations necessary for conducting the licensed activity. These may include: notarial deed, excerpt from the land and mortgage register, extract from the land register, lease agreements, lending agreements, purchase invoices for energy generation equipment, handover/acceptance protocols for generation equipment, etc.;
  2. Description of the parameters and technical condition of energy generation equipment (boilers/engines/turbines/electric generators), including information on the type of fuel used;
  3. Diagram of the set of devices comprising the cogeneration unit, with indication of the balance boundary;
  4. Administrative ruling on land development conditions or administrative ruling on the location of a public purpose investment;
  5. Building permit decision should cover the equipment, installations, and networks;
  6. Attach documents confirming completion of construction and commencement of operation of the facility (depending on the conditions specified in the building permit). These may include: occupancy permit or notification to the competent building supervision authority of construction completion, along with your statement confirming no objection was raised to the notification. If it is not possible to present the occupancy permit or building permit with the notification of construction completion, submit the administrative ruling on land development conditions or the administrative ruling on the location of a public purpose investment, or information on compliance with the local spatial development plan. In such cases, attach information from the architectural and construction administration authority, building supervision authority, or municipality regarding the date of construction and the inability to obtain a copy of the aforementioned decisions or information on their issuance. Also attach confirmation from the building supervision authority that the facility is not an unauthorized construction and complies with applicable legal requirements;
  7. Attach decisions and protocols issued by the Office of Technical Inspection. These should authorize the operation of energy generation equipment;
  8. If required for your installation, submit: integrated permit, permit for waste generation, and permit for the release of pollutants into the air;
  9. Documents confirming the installed electric capacity of the cogeneration unit, such as: photos of nameplates of electric generators or technical-operational documentation of the generators;
  10. Submit documents issued by the electricity system operator to whose grid your cogeneration unit is connected:
  • Technical conditions for connection to the electricity grid (so-called grid connection conditions) or connection agreement
  • Technical inspection, approval, and commissioning protocol for energy equipment
  • Protocol verifying the correct operation of metering and settlement systems – so-called OTS order protocol
  1. Power output diagram – required in the case of a cogeneration unit that also constitutes a renewable energy installation. The diagram should indicate:
  • Points of measurement of the amount of electricity generated
  • Ownership boundaries of networks, equipment, and installations belonging to you and the electricity system operator
  • All generation equipment (belonging to you or a third party) from which energy is or may be exported via the given connection
  1. Biomass/biogas specification should include a precise description of its parameters: type, form, and origin, and in the case of biogas – also the type and composition of substrates and a description of the production process (e.g. type of fermentation, method of acquisition);
  2. Sample (preliminary) purchase agreements for the given type of biomass, in the case of units using biomass;
  3. A detailed and legible diagram of the fuel feeding system should also include any auxiliary fuels and fuels supporting the combustion process;
  4. Results of operational tests confirming the possibility of using a specific type (group) of biomass in your cogeneration unit. The result should be approximately 3 pages long;
  5. Manufacturer’s opinion on the generation equipment confirming the possibility of burning only biomass, including information on the use of any auxiliary fuels and fuels supporting the combustion process;
  6. Submit information on the fuel used for electricity generation and a statement on whether auxiliary fuel is used or not used in the renewable energy installation;
  7. A document confirming that the technical safeguards in place prevent electricity generation from auxiliary fuel. This document should be prepared by an independent external entity based on an audit of the installation – in the case of a dedicated biomass combustion installation using auxiliary fuel;
  8. Submit authenticated documentation (in 2 copies) in the case of a cogeneration unit that constitutes:
  • A multi-fuel combustion installation
  • A thermal waste conversion installation
  • A hybrid system with installed electric capacity above 20 MW
  • A dedicated biomass installation with installed electric capacity above 20 MW
  1. Opinion on the above authenticated documentation (prepared by an independent third party based on an audit of the installation) – 1 copy.

 

Documents confirming the availability of financial resources
  1. A summary of annual projected revenues and costs for the activity covered by the licensing application, for a period of at least 3 years;
  2. Financial statements from the last 3 years (annual PIT returns for natural persons or partners in civil law partnerships, balance sheets and profit and loss accounts for other entities). If you have been operating for less than three years, attach documents covering the period since the start of your business activity;
  3. Documents confirming possession or the ability to obtain financial resources sufficient for the proper performance of the licensed activity (bank guarantees, insurance guarantees, and guarantee agreements);
  4. A certificate from the competent tax office confirming that the entrepreneur has no outstanding liabilities to the state budget (or indicating the status of any such liabilities). In the case of civil law partnerships, submit separate certificates for each partner and for the partnership itself. The certificate should also include information on:
  • enforcement proceedings in public administration and proceedings related to fiscal crimes or offenses
  • the titles and periods from which any arrears originate
  1. A certificate from the relevant branch of the Social Insurance Institution (ZUS) confirming that the entrepreneur has no outstanding social insurance contributions. Alternatively, attach a certificate stating that the entrepreneur is not listed in the register of contribution payers — applicable when the business activity did not require registration with ZUS. In the case of civil law partnerships, submit separate ZUS certificates for each partner and for the partnership. The certificate should be obtained no earlier than 3 months before submitting the application;
  2. A certificate from the bank where the entrepreneur’s primary account is held. It should specify the turnover volume and include information on any loans granted to the entrepreneur, as well as confirmation that the account is not subject to enforcement titles.

     

Information for foreign entrepreneurs applying for a license
  1. Entrepreneurs from European Union member states, Switzerland, and member states of the European Free Trade Association (EFTA) may conduct licensed activities in Poland directly, i.e. without establishing a branch. In such cases, entrepreneurs must submit an excerpt from the relevant equivalent of the Polish National Court Register (KRS) in the country where the company is registered;
  2. Certificates of no criminal record for persons authorized to represent the foreign entrepreneur and for supervisory board members should be obtained from:
  • the Polish National Criminal Register
  • the equivalent register maintained in the country of company registration, or from the Polish National Criminal Register via the ECRIS system
If these persons are not citizens of the country where the company is registered, the certificates should be issued by the competent authorities of the countries of which these persons are citizens;
  1. A certificate of no criminal record for the enterprise (as a collective entity) should be obtained from the Polish National Criminal Register and from the equivalent register maintained in the country of company registration;
  2. A certificate of no criminal record for entities that have a significant influence on your company or exercise control or joint control over it should be obtained from:
  • the Polish National Criminal Register
  • the equivalent register maintained in the country of registration of your company (if such registers exist), and from the equivalent register maintained in the country of registration or citizenship of the entities concerned
  1. A tax authority ruling on the assignment of a tax identification number may originate from the country of company registration (a document confirming assignment of a NIP number in Poland is also accepted). The same applies to documents confirming registration of the entrepreneur as a VAT taxpayer;
  2. Compliance of submitted documents with the law of the place of issuance must be confirmed in accordance with the apostille clause.
Documents submitted in a foreign language must be translated into Polish by a sworn translator. Documents submitted to the Energy Regulatory Office (URE) should be originals. Instead of the original, you may submit a copy of the document, but its conformity with the original must be certified by a notary or by an attorney, legal advisor, patent attorney, or tax advisor. As proof, you may submit a photocopy of the document signed by the entrepreneur or persons authorized to represent them. Exceptions apply to documents for which URE has explicitly requested submission of the original. In case of doubt, the President of URE may request the party to present the original document or a certified copy in accordance with Article 76a § 1 or 2 of the Code of Administrative Procedure.
Deadline
You must obtain the license before commencing business activity in the field of electricity generation in cogeneration.

2. The authority will verify whether your application is complete

If any deficiencies are found in the application, the authority will request you to correct them within a specified deadline. You will have a maximum of 30 days to do so, counted from the date of receiving the request. If you fail to correct the deficiencies within the deadline, the authority will leave the application unprocessed — meaning you will not be granted a license.
If you fail to pay the stamp duty for the issuance of the license, the authority will set a deadline for payment — between 7 and 14 days. If you do not pay within the specified time, your application will be returned.
Note: Failure to pay the stamp duty for the granted power of attorney does not result in the return of the application. The Energy Regulatory Office will continue to process the case, but will send information about the missing payment to the city office whose account should receive the fee. The city office will initiate enforcement proceedings.

3. The authority will initiate proceedings for issuing the license

If your application for a license is free of formal deficiencies or you have corrected them, the Energy Regulatory Office will initiate administrative proceedings. The licensing process may not be limited to just you and the authority — the authority will notify all parties to the proceedings about the initiation.
The Energy Regulatory Office may summon you (as well as other parties or your attorney) to participate in actions taken and to provide explanations — in person, through an attorney, or in writing (in accordance with Articles 50–56 of the Code of Administrative Procedure).

4. The authority will assess whether it can issue the license

The Energy Regulatory Office will request an opinion from the relevant Regional Government Board, based on the location of the installation. The Board has 14 days to issue an opinion in the form of an administrative ruling. If it fails to do so within this period, the Energy Regulatory Office will assume that the opinion is positive.
The authority will evaluate your application
The Energy Regulatory Office will assess the submitted documents. Before making a decision on granting the license, it may verify the facts stated in the application. This is to determine whether you meet the conditions for conducting the licensed business activity and whether you provide sufficient assurance of proper performance of such activity.

Additional financial security to satisfy third-party claims

The Energy Regulatory Office may condition the issuance of the license on the submission of additional financial security. This is intended to satisfy potential claims from third parties, which may arise from improper conduct of the licensed activity — for example, environmental damage. In such a case, you will receive an administrative ruling requiring the submission of security. You cannot appeal this ruling separately — it may only be challenged in an appeal against the license decision.

The authority will notify parties about the collection of all case materials

Notified parties may review the case files and submit any motions or objections (in accordance with Article 10 § 1 of the Code of Administrative Procedure). All parties have the right to participate at every stage of the proceedings and to express their views — before the license is granted — on the collected materials and evidence. You may also do so. The licensing authority, when informing about the opportunity to review the collected evidence, will also indicate any conditions that have not yet been met or demonstrated, and whose failure to fulfill may result in a decision that does not align with the applicant’s request. Within the deadline set for commenting on the collected evidence and materials, the party may submit additional evidence to demonstrate compliance with these conditions (Article 79a of the Code of Administrative Procedure).

Important

If, during the licensing process, you are charged with committing a crime related to your business activity, the Energy Regulatory Office will suspend the proceedings. The suspension will last until the preparatory and court proceedings are concluded.
Suspension will also occur if charges are brought against supervisory board members or persons authorized to represent your company.

Documents

1. Opinion regarding the license

You will receive the document as:
Original

2. Administrative ruling imposing the obligation to provide financial security by the applicant

You will receive the document as:
Original

3. Notification to parties about the conclusion of the evidentiary proceedings and the possibility to review the documentation

You will receive the document as:
Original

5. You will receive a license for electricity generation

If your application meets the requirements set out in the regulations, the authority will issue you a license. You will receive it in the form of a decision.

The Energy Regulatory Office will issue a decision of refusal if you do not meet the legal requirements. The authority will inform the European Commission — via the Minister of Energy — about the refusal. The notification will include the reasons for denying the license.

Once the license is granted, the authority will enter your company into the register of enterprises holding a license for electricity generation. This register is maintained by the Energy Regulatory Office.

When you will not receive a license
The Energy Regulatory Office will refuse to grant a license if:
  • Your company is undergoing bankruptcy or liquidation proceedings;
  • In the last 3 years, your license for an activity regulated by the Energy Law was revoked due to reasons listed in Article 41(3) of that law — for example, gross violation of license conditions or other conditions for conducting licensed business activity;
  • In the last 3 years, you were removed from the register of regulated activities after receiving a ban on conducting the registered activity, due to:
    • Submission of a false statement regarding compliance with legal requirements for conducting the activity
    • Failure to correct violations within the deadline set by the authority
    • Gross violation of the conditions for conducting the activity
  • You were convicted by a final court judgment for a crime related to business activity conducted under the Energy Law. If the applicant is a company, foreign entrepreneur, or branch of a foreign entrepreneur, persons authorized to represent these entities or members of their supervisory boards must also not have been convicted;
  • You are not registered as a VAT taxpayer;
  • Another entity that has significant influence over your company or exercises control or joint control was convicted by a final judgment in the last 3 years for a crime or fiscal offense related to the business activity conducted under the Energy Law. Issues of control are regulated by the Accounting Act of 29 September 1994.

Documents

1. Licence for Electricity Generation in Cogeneration (CHP)
You will receive the document as:
Original

Additional Information

The license should specify:
  1. The entity and its registered office or place of residence;
  2. The subject and scope of the licensed activity;
  3. The start date of the licensed activity and the conditions for its performance;
  4. The validity period of the license;
  5. Specific conditions for the performance of the licensed activity aimed at ensuring proper service to customers, in particular regarding:
    • Ensuring the capacity to supply fuels or energy continuously and reliably, while meeting the quality requirements specified in the regulations issued under Article 9(1–4), (7), and (8) of the Energy Law;
    • Notifying the President of the Energy Regulatory Office of failure to commence, suspension, or limitation of the licensed activity during the license validity period;
  6. Environmental protection measures during and after the cessation of the licensed activity;
  7. The number in the register of entrepreneurs or the register of business activity, and the tax identification number (NIP) – if the entrepreneur has such a number.
The license for conducting business activity in the field of electricity generation in cogeneration should also define the conditions for ceasing the activity of the energy enterprise after the license expires or is revoked.

 

How much will you pay

PLN 616

The stamp duty must be paid at the time of submitting the application for the license. As proof of payment, you may attach a printout confirming the bank transaction. The fee should be paid to the account of the Ochota District Office – City of Warsaw. You may also make the payment at the cash desk of this office.

Stamp duty is not required from, among others, local government budgetary units and public benefit organizations.

Appointing a representative

f you wish to be represented by an attorney, remember to attach the power of attorney and proof of payment of the stamp duty for the power of attorney (PLN 17). You do not need to pay this fee if the power of attorney is granted to your spouse, children, parents, or siblings.

How long will you wait

No longer than one month. The deadline may be extended to two months — you will be informed if that happens.

How to appeal

You may appeal the decision regarding the license for electricity generation in cogeneration. You have 2 weeks to do so — counted from the date you received the decision. Submit the appeal via the Energy Regulatory Office. It will be reviewed by the District Court in Warsaw – Court of Competition and Consumer Protection.
Your appeal should include:
  • The case number and reference of the contested decision
  • A list of objections and a brief justification
  • Indication of evidence
  • A statement that you request the decision to be repealed or amended in whole or in part
The court fee for the appeal is PLN 1000. The appeal is processed in accordance with the provisions of the Code of Civil Procedure.
If the Energy Regulatory Office considers your appeal justified, it may — without forwarding the case files to the court — repeal or amend the decision in whole or in part. You will receive a new decision, which you may also appeal.

Good to know

Obtaining other documents and permits

Obtaining a license for electricity generation in cogeneration does not exempt you from the obligation to obtain other licenses and permits required by separate regulations.
For example, if you hold a license for electricity generation in cogeneration, you must also obtain a license for electricity transmission if you intend to transmit the energy.

How long is the license valid

The license is granted for a fixed period — not shorter than 10 years and not longer than 50 years. You may request a shorter validity period — but you must indicate this in your application.

The Energy Regulatory Office may require you to continue the licensed activity after the license expires, if it is necessary for the public interest. In such cases, the license may be extended for no longer than 2 years. If your activity under the license results in losses, you are entitled to compensation for those losses.

You may apply for an extension of the license validity. Submit the application no later than 18 months before the license expires.

License fees

 

After receiving the license for electricity generation in cogeneration, you are required to calculate and pay an annual license fee. The fee must be paid by April 15 each year. License fees are regulated by the Regulation of the Council of Ministers of 9 November 2018 on license fees.

License amendments

 

Submit an application to amend the license if any of the following change:

  • Your company name

  • Address of your registered office or your residential address

  • Company registration number (KRS or its equivalent in other countries)

  • Tax identification number (NIP)

Submit the application no later than 7 days from the date the change occurred.

The Energy Regulatory Office may also amend the license conditions at your request — for example, if you intend to generate electricity in a different way.

What else does the license provide

 

If you generate electricity in high-efficiency cogeneration and hold a license for electricity generation in cogeneration, you:

  • Have priority in the transmission or distribution of the generated electricity. You may request its acceptance by the electricity system operator to whose grid your generation units are directly connected

  • May benefit from support mechanisms described in the Act of 14 December 2018 on promoting electricity from high-efficiency cogeneration

{"register":{"columns":[]}}