A photovoltaic system with a total installed capacity of up to 150 kW is subject to a shorter path of required administrative procedures. Such systems are exempt from the obligation to obtain a construction permit. The list of necessary permits for a small PV system will also depend on whether it is a ground-mounted or rooftop system.
For photovoltaic systems with a total installed capacity exceeding 150 kW, it is always necessary to obtain a construction permit. The remaining required procedures depend on the location and the size of the area occupied by the system.