Large-Scale Wind System (with a Capacity Exceeding 1 MW)
Steps in the investment process for implementing this system
The investment process for large-scale wind power systems requires obtaining specific approvals, permits, and decisions. It concludes with obtaining a licence for the generation of electricity from renewable energy sources (RES).
Step 1 – Obtaining a decision on environmental conditions
Obtaining a decision on environmental conditions (environmental decision) is, in most cases, the first stage in the investment and construction process for an onshore wind energy system.
Decision on environmental conditions
Step 2 – Spatial planning
At this stage, the investment is implemented through the adoption of a local spatial development plan (MPZP) (if none exists), amendment of the MPZP (if the existing plan does not provide for the location of the given type of RES system), or adoption of an integrated investment plan (ZPI) together with an urban planning agreement.
Step 3 – Obtaining conditions for connection to the electricity grid
Conditions for connection to the electricity grid are a type of document issued by the distribution or transmission system operator, specifying technical details related to connecting the wind power system and constituting the operator’s obligation to sign a grid connection agreement with the investor. These conditions effectively provide a “temporary reservation of capacity in the grid” for the given project.
If, within 24 months from the date of receipt of the connection conditions, the generator does not conclude a grid connection agreement, the conditions expire and no longer constitute an obligation to conclude such an agreement.
A detailed description of this procedure can be found at the following link:
Application for issuance of conditions for connection to the electricity grid
Step 4 – Obtaining a construction permit
The construction permit is an element of the investment process that forms the basis for commencing construction works on the wind power system. Without this decision, construction works cannot begin, nor can an application for an occupancy permit be submitted.
Construction permit
Note: For certain large-scale wind systems, prior to obtaining a construction permit, it may also be necessary to report the wind farm as an air navigation obstacle (to the President of the Civil Aviation Authority, the Minister of National Defence, and the minister responsible for internal affairs).
Reporting air navigation obstacles
Step 5 – Operational notification
After completing the construction of the wind system, in order to commence its operation, it is necessary to submit an operational notification. This procedure confirms the possibility of legally operating the facility in accordance with its intended purpose.
Additionally, in parallel with submitting the operational notification, pursuant to Article 76(4) of the Environmental Protection Law, the provincial environmental inspector must be notified 30 days prior to the planned commissioning date of the system and the planned completion of its start-up.
Operational notification
Step 6 – Obtaining a licence for the generation of electricity from RES
The commencement of electricity generation and sale is possible after the investor obtains a licence for the generation of electricity from renewable energy sources.
Licence for the Generation of Electricity from Renewable Energy Sources (RES)