Photovoltaic Micro-System up to 6.5 kW

Steps in the investment process for implementing this system

The installation of a photovoltaic system with a total installed capacity of up to 6.5 kW is maximally simplified in terms of formal requirements. For on-grid systems (connected to the power grid), only a notification of the micro-system or obtaining grid connection conditions is required.

Step 1 – Notification of the micro-system / obtaining grid connection conditions

If the capacity of the micro-system is equal to or less than the connection capacity of the facility where it will be installed, a notification of connection to the grid is submitted. The operator will complete the connection within 30 days from the date of notification.

However, if the capacity of the micro-system exceeds the connection capacity of the facility, an application for grid connection conditions must be submitted.

Detailed description of the micro-system notification process is available at the following link:
 
Detailed description of the process of obtaining grid connection conditions is available at the following link: