Procedures – offshore wind farms
-
Permit decision for the erection or use of artificial islands, structures and equipment in Polish maritime areas
-
Permit to install and maintain cables within internal sea waters and the territorial sea and approval for installation and maintenance of cables in the exclusive economic zone
-
Decisions approving expert assessments and plans concerning maritime navigation safety, personnel safety, and marine environmental protection
-
Decisions approving expert assessments in the field of communication systems, maritime safety, protection of the state border at sea, and national defence
-
Expert opinion on design and workmanship conformity submitted to the transmission system operator
-
Certification of offshore wind farms and the set of equipment for power evacuation
-
Verification of location possibilities in the Spatial Development Plan for Internal Sea Waters, Territorial Sea and Exclusive Economic Zone (PZPPOM) and Annexes 1 and 2 to the Act on Promoting Electricity Generation in Offshore Wind Farms (u.p.m.f.w.)
-
Decision on the approval of geological documentation for an offshore wind farm