Back

Micro-Scale Ground-Mounted Wind System

Steps in the investment process for implementing this system

The installation of ground-mounted micro-scale wind systems is significantly simplified compared to larger-capacity systems of this type. However, it still requires, among other things, obtaining a location approval and a construction permit.

Step 1 – Spatial planning

At this stage, the investment is implemented through the adoption of a local spatial development plan (MPZP) (if none exists), amendment of the MPZP (if the existing plan does not provide for the location of the given type of RES system), or adoption of an integrated investment plan (ZPI) together with an urban planning agreement.

Detailed descriptions of the procedures discussed in this step can be found at the following links:

Step 2 – Obtaining a construction permit

The construction permit is an element of the investment process that forms the basis for commencing construction works on the wind power system. Without this decision, construction works cannot begin, nor can an application for an operational notification be submitted.

A detailed description of this procedure can be found at the following link:
Construction permit

Step 3 – Operational notification

After completing the construction of the wind system, in order to commence its operation, it is necessary to submit an operational notification. This procedure confirms the possibility of legally operating the facility in accordance with its intended purpose.

It is important to note that for a micro-scale wind system exceeding 30 meters in height or located in protected areas (pursuant to §3(6)(1)(a) of the Regulation of the Council of Ministers of 10 August 2023 amending the Regulation on projects that may significantly affect the environment), the provincial environmental inspector must be notified 30 days prior to the planned commissioning date and completion of start-up, in accordance with Article 76(4) of the Environmental Protection Law.

A detailed description of this procedure can be found at the following link:
Operational notification

Step 4 – Micro-system notification / obtaining conditions for connection

If the capacity of the micro-system is less than or equal to the connection capacity of the building on which it will be installed, a notification of connection to the grid is submitted. The operator connects the system within 30 days from the date of notification.

If the connection capacity of the micro-system exceeds the connection capacity of the building on which it is installed, an application for issuance of conditions for connection is required.

Detailed descriptions of these procedures can be found at the following links:
{"register":{"columns":[]}}