The investment process for a micro-scale wind system with a height exceeding 3 meters, in addition to micro-system notification or obtaining conditions for connection, also includes an additional construction procedure.

Step 1 – Notification of construction with a building design

For the construction of wind systems classified as micro-systems with a height exceeding 3 meters, the obligation to submit a notification of construction with a building design applies.

A detailed description of this procedure can be found at the following link:
Notification of construction with a building design

Step 2 – Micro-system notification / obtaining conditions for connection

If the capacity of the micro-system is less than or equal to the connection capacity of the building on which it will be installed, a notification of connection to the grid is submitted. The operator connects the system within 30 days from the date of notification.

If the connection capacity of the micro-system exceeds the connection capacity of the building on which it is installed, an application for issuance of conditions for connection is required.

Below is a link to the page describing the process of micro-system notification:
Micro-system notification

Below is a link to the page describing the process of obtaining conditions for connection:
Application for issuance of conditions for connection to the electricity grid