Micro-Scale Rooftop Wind System With a Height of Up to 3 m
Steps in the investment process for implementing this system
The installation of a micro-scale wind system with a height of up to 3 meters is maximally simplified. In the case of on-grid systems (connected to the grid), only the notification of the micro-system or obtaining conditions for connection is required.
Step 1 – Micro-system notification / obtaining conditions for connection
If the capacity of the micro-system is less than or equal to the connection capacity of the building on which it will be installed, a notification of connection to the grid is submitted. The operator connects the system within 30 days from the date of notification.
If the connection capacity of the micro-system exceeds the connection capacity of the building on which it is installed, an application for issuance of conditions for connection is required.
Below is a link to the page describing the process of micro-system notification:
Micro-system notification
Micro-system notification
Below is a link to the page describing the process of obtaining conditions for connection:
Application for issuance of conditions for connection to the electricity grid
Application for issuance of conditions for connection to the electricity grid